Finally!!! Making some progress now. The mud room addition is nearly done-insulation, sheet rock, siding and additional window completed this week. The siding is nice shaker siding, but you can't see it well in these night time pictures. A temporary door had to be put on because the pretty glass one we picked out was ordered in the wrong size :( Of course these old houses don't have standard size ANYTHING- Our contractor is learning that the hard way. Our new cement stairs finally got poured last week. They don't look like much covered in mud and rain. We are planning to move to the rental the first week of December, wish us luck. Oh and next week they are replacing our main water line, so we will be completely with out water for at least 2 days- can't wait for that!

The new addition makes the back of our place look like an abandoned crack house- lovely.